New external network of settlements of the Municipal Unit of Ellisponto, Kozani

Customer

Municipality of Kozani

Year

Budget

6.000.000 €

The project included the construction of a new external water supply network, which supplies the settlements of the Municipality of Ellispontos (except Drepano, Ag. Demetrios, Akrini and Ryaki), with parallel supply from the springs of Zoodochos Pigi, the springs of Ermakias and during periods of high demand from the reservoir of Ag. Paraskevi of the city of Kozani.

In more detail:
New interconnection pipeline of the Zoodochos Pigi springs pipeline with the Kozani - Ermakia pipeline from HDPE pipe F355 (1070.00 m) and from cast iron pipe DN300 (14.640 m).
Discharge pipeline of the Zoodochos spring network (HDPE pipe F225 - 1.000,00 m), pipeline for the supply of the existing reservoir of the community Leventis (HDPE pipe F75 - 2,700.00 m), pipeline supplying the existing reservoir of the community of Agioi Theodoroi (HDPE pipe F90 - 2,100.00 m), pipeline connecting the main pipeline with the existing pumping station of Avgi (HDPE pipe F75 - 980.00 m).

Also, a pipeline connecting the main pipeline with the well of Voskochori, for the supply of the settlements of Voskochori, Agios Charalambos and Tetralofos (HDPE pipe F225 - 1. 340.00 m), pipeline interconnecting the main pipeline with the existing reservoir of Kapnochori (HDPE pipe F140 , 2.350.00 m), pipeline interconnecting the main pipeline with the existing reservoir of Killada (HDPE pipe F160 - 1. 170,00 m), pipeline connecting the main pipeline to the existing tank of Galani (HDPE pipe F90 - 3. 600,00 m), pipeline linking the new valley reservoir with the overflow pipeline of the existing valley reservoir (HDPE pipe F160 - 230,00 m), pipeline linking the new valley reservoir with the pipeline supplying Kissa from the existing valley reservoir (HDPE pipe F160 - 230,00 m)

Work is also being carried out for the reconstruction of the Voskhori well which includes the replacement of the electromechanical equipment and the maintenance - reconstruction of the walls of the chambers, a new well at the departure point of the main pipeline (Polymylou), with a surface area of 36m2 and an estimated volume of 25m3, a new reservoir in the valley that will cover an area of 121m2 and will have a volume of 250m3.